Code specifying type of date or time, or both date and time

You’ll find these values used mostly in DTM-01, DTP-01, ACK-04, ZA-04, SCH-05 data elements.

Examples

011 Date Shipped  DTM*011*20190729
001 Cancel After Date    
DTM*001*20190730
106 Required By Date    DTM*106*20190731
063 Do Not Deliver After    
DTM*063*20190731
037 Ship Not Before Date    
DTM*037*20190801
067 Current Schedule Delivery Date    DTM*067*20190815
068 Current Schedule Ship Date    DTM*067*20190815
405 Production Date    DTM*405*20190807
010 Requested Ship Date    DTM*010*20190801
ZZZ Mutually Defined   DTM*ZZZ*20190601

 

Date and Time Qualifiers (EDI Data Element ID 374)

 

CODE DEFINITION & EXPLANATION
001 Cancel After
002 Delivery Requested
003 Invoice
004 Purchase Order
005 Sailing
006 Sold
007 Effective
008 Purchase Order Received
009 Process
010 Requested Ship
011 Shipped
012 Terms Discount Due
013 Terms Net Due
014 Deferred Payment
015 Promotion Start
016 Promotion End
017 Estimated Delivery
018 Available
019 Unloaded
020 Check
021 Charge Back
022 Freight Bill
023 Promotion Order – Start
024 Promotion Order – End
025 Promotion Ship – Start
026 Promotion Ship – End
027 Promotion Requested Delivery – Start
028 Promotion Requested Delivery – End
029 Promotion Performance – Start
030 Promotion Performance – End
031 Promotion Invoice Performance – Start
032 Promotion Invoice Performance – End
033 Promotion Floor Stock Protect – Start
034 Promotion Floor Stock Protect – End
035 Delivered
036 Expiration
Date coverage expires
037 Ship Not Before
038 Ship No Later
039 Ship Week of
040 Status (After and Including)
041 Status (Prior and Including)
042 Superseded
043 Publication
044 Settlement Date as Specified by the Originator
045 Endorsement Date
046 Field Failure
When a component causes a system to fail at a customer site
047 Functional Test
When assembly was tested
048 System Test
When the finished system was tested
049 Prototype Test
When the prototype system or assembly was tested
050 Received
051 Cumulative Quantity Start
052 Cumulative Quantity End
053 Buyers Local
054 Sellers Local
055 Confirmed
056 Estimated Port of Entry
057 Actual Port of Entry
058 Customs Clearance
059 Inland Ship
060 Engineering Change Level
061 Cancel if Not Delivered by
062 Blueprint
063 Do Not Deliver After
064 Do Not Deliver Before
065 1st Schedule Delivery
066 1st Schedule Ship
067 Current Schedule Delivery
068 Current Schedule Ship
069 Promised for Delivery
070 Scheduled for Delivery (After and Including)
071 Requested for Delivery (After and Including)
072 Promised for Delivery (After and Including)
073 Scheduled for Delivery (Prior to and Including)
074 Requested for Delivery (Prior to and Including)
075 Promised for Delivery (Prior to and Including)
076 Scheduled for Delivery (Week of)
077 Requested for Delivery (Week of)
078 Promised for Delivery (Week of)
079 Promised for Shipment
080 Scheduled for Shipment (After and Including)
081 Requested for Shipment (After and Including)
082 Promised for Shipment (After and Including)
083 Scheduled for Shipment (Prior to and Including)
084 Requested for Shipment (Prior to and Including)
085 Promised for Shipment (Prior to and Including)
086 Scheduled for Shipment (Week of)
087 Requested for Shipment (Week of)
088 Promised for Shipment (Week of)
089 Inquiry
090 Report Start
091 Report End
092 Contract Effective
093 Contract Expiration
094 Manufacture
095 Bill of Lading
096 Discharge
097 Transaction Creation
098 Bid (Effective)
099 Bid Open (Date Bids Will Be Opened)
100 No Shipping Schedule Established as of
101 No Production Schedule Established as of
102 Issue
103 Award
104 System Survey
105 Quality Rating
106 Required By
107 Deposit
108 Postmark
109 Received at Lockbox
110 Originally Scheduled Ship
111 Manifest/Ship Notice
112 Buyers Dock
113 Sample Required
114 Tooling Required
115 Sample Available
116 Scheduled Interchange Delivery
118 Requested Pickup
119 Test Performed
120 Control Plan
121 Feasibility Sign Off
122 Failure Mode Effective
124 Group Contract Effective
125 Group Contract Expiration
126 Wholesale Contract Effective
127 Wholesale Contract Expiration
128 Replacement Effective
129 Customer Contract Effective
130 Customer Contract Expiration
131 Item Contract Effective
132 Item Contract Expiration
133 Accounts Receivable – Statement Date
134 Ready for Inspection
135 Booking
136 Technical Rating
137 Delivery Rating
138 Commercial Rating
139 Estimated
140 Actual
141 Assigned
When the service request was supplied to the service provider or agency
142 Loss
When the insured experienced the theft, damage, or casualty to a given property
143 Due Date of First Payment to Principal and Interest
The date first mortgage payment on the principal and interest on a mortgage loan is due
144 Estimated Acceptance
145 Opening Date
146 Closing Date
147 Due Date Last Complete Installment Paid
The date last complete principal and interest mortgage payment made was due
148 Date of Local Office Approval of Conveyance of Damaged Real Estate Property
The date local office approves of the transfer of damaged property
149 Date Deed Filed for Record
The date the formal document (deed) used to transfer title to real estate is filed for record with the recording authority
150 Service Period Start
151 Service Period End
152 Effective Date of Change
Date on which the change went into effect
153 Service Interruption
154 Adjustment Period Start
155 Adjustment Period End
156 Allotment Period Start
157 Test Period Start
158 Test Period Ending
159 Bid Price Exception
160 Samples to be Returned By
161 Loaded on Vessel
162 Pending Archive
163 Actual Archive
164 First Issue
165 Final Issue
166 Message
167 Most Recent Revision (or Initial Version)
168 Release
169 Product Availability Date
170 Supplemental Issue
171 Revision
172 Correction
173 Week Ending
174 Month Ending
175 Cancel if not shipped by
176 Expedited on
177 Cancellation
Date on which the coverage or service is no longer in force
178 Hold (as of)
179 Hold as Stock (as of)
180 No Promise (as of)
181 Stop Work (as of)
182 Will Advise (as of)
183 Connection
184 Inventory
185 Vessel Registry
186 Invoice Period Start
When the billing period covered by an invoice begins
187 Invoice Period End
When the billing period covered by an invoice ends
188 Credit Advice
189 Debit Advice
190 Released to Vessel
191 Material Specification
192 Delivery Ticket
193 Period Start
194 Period End
195 Contract Re-Open
196 Start
197 End
198 Completion
Date when the activity was completed
199 Seal
200 Assembly Start
201 Acceptance
202 Master Lease Agreement
203 First Produced
The date of first production of hydrocarbon from a well for the purpose of sales or on-lease use
204 Official Rail Car Interchange (Either Actual or Agreed Upon)
205 Transmitted
206 Status (Outside Processor)
When outside processor established the status of the material
207 Status (Commercial)
When producer established the status of the material
208 Lot Number Expiration
209 Contract Performance Start
210 Contract Performance Delivery
211 Service Requested
When warranty repair service was requested
212 Returned to Customer
213 Adjustment to Bill Dated
214 Date of Repair/Service
215 Interruption Start
When an interruption in the airplane fueling process began
216 Interruption End
217 Spud
When drilling started for a well
218 Initial Completion
When well was originally completed
219 Plugged and Abandoned
When a well was plugged and abandoned after discontinuing to produce
220 Penalty
Range of penalty period
221 Penalty Begin
Date on which penalty period begins
222 Birth
223 Birth Certificate
224 Adoption
225 Christening
226 Lease Commencement
227 Lease Term Start
228 Lease Term End
229 Rent Start
230 Installation
231 Progress Payment
232 Claim Statement Period Start
233 Claim Statement Period End
234 Settlement Date
235 Delayed Billing (Not Delayed Payment)
236 Lender Credit Check
237 Student Signed
238 Schedule Release
Planned release date for an item or product
239 Baseline
The baseline or original plan that progress is measured against
240 Baseline Start
The start date of baseline or original plan
241 Baseline Complete
The complete date of the baseline or original plan
242 Actual Start
The actual start date for a task or activity
243 Actual Complete
The actual complete date for a task or activity
244 Estimated Start
The revised plan or estimate of the start date for a task or activity
245 Estimated Completion
The revised plan or estimate of the complete date for a task or activity
246 Start no earlier than
Fixed start date for a task or activity – cannot begin before this date
247 Start no later than
Fixed start date for a task or activity – cannot begin after this date
248 Finish no later than
Fixed finish date for a task or activity – cannot end after this date
249 Finish no earlier than
Fixed finish date for a task or activity – cannot end before this date
250 Mandatory (or Target) Start
Fixed start date – must begin on this date
251 Mandatory (or Target) Finish
Fixed finish date – must finish on this date
252 Early Start
The earliest date a task or activity can begin
253 Early Finish
The earliest date a task or activity can end
254 Late Start
The latest date a task or activity can begin
255 Late Finish
The latest date a task or activity can end
256 Scheduled Start
The scheduled start for a task or activity based on resource needs
257 Scheduled Finish
The scheduled finish for a task or activity based on resource needs
258 Original Early Start
The saved baseline or planned early start before current changes
259 Original Early Finish
The saved baseline or planned early finish before current changes
260 Rest Day
A non-working day such a Saturday or Sunday
261 Rest Start
The beginning of a range for rest days (from)
262 Rest Finish
The end of a range of rest days (to)
263 Holiday
A non-working day reserved for a company or national holiday
264 Holiday Start
The beginning of a range for holidays (from)
265 Holiday Finish
The end of a range of holidays (to)
266 Base
The start of base date for a calendar reference – all dates fall after it
267 Timenow
The current reporting period reference, or current status
268 End Date of Support
269 Date Account Matures
270 Date Filed
271 Penalty End
Date on which penalty period ends
272 Exit Plant Date
Date at which the product leaves the manufacturing site
273 Latest On Board Carrier Date
Latest date on which the cargo must be on board the carrier
274 Requested Departure Date
275 Approved
Date report was approved by contractor representative
276 Contract Start
The start date for a contract
277 Contract Definition
The date the contract was definitized
278 Last Item Delivery
The date the last item will be delivered to the customer
279 Contract Completion
The finish date for a contract
280 Date Course of Orthodontics Treatment Began or is Expected to Begin
281 Over Target Baseline Month
The date a budget baseline went over the target budget amount
282 Previous Report
The date a previous report was submitted
283 Funds Appropriation – Start
The date that funds appropriation begins
284 Funds Appropriation – End
The date that funds appropriation ends
285 Employment or Hire
Date on which the subscriber or dependent is hired
286 Retirement
Date on which the subscriber became retired
287 Medicare
Range of dates when the subscriber or dependent is eligible to receive Medicare benefits
288 Consolidated Omnibus Budget Reconciliation Act (COBRA)
Range of COBRA coverage
289 Premium Paid to Date
Range of dates for which premium has been paid
290 Coordination of Benefits
Range for which coordination of benefits between insurers applies
291 Plan
Range of dates for which the plan is in effect
292 Benefit
Range of benefit coverage
293 Education
Range of dates when the subscriber or dependent is a student
294 Earnings Effective Date
Date on which earnings become effective for applicable benefits
295 Primary Care Provider
Range of dates for which the services of the primary care provider are in effect
296 Initial Disability Period Return To Work
297 Initial Disability Period Last Day Worked
298 Latest Absence
Latest occurrence of which the subscriber did not report to work
299 Illness
300 Enrollment Signature Date
Date subscriber or dependent signed policy enrollment card
301 Consolidated Omnibus Budget Reconciliation Act (COBRA) Qualifying Event
Date of the qualifying event which initiated COBRA benefits
302 Maintenance
Date on which the maintenance was performed
303 Maintenance Effective
Date on which the maintenance is effective
304 Latest Visit or Consultation
Date subscriber or dependent last visited or consulted with a physician
305 Net Credit Service Date
Date assigned by the employer to an employee who previously worked for them
306 Adjustment Effective Date
Date on which the adjustment went into effect
307 Eligibility
Range of dates when the subscriber or dependent were eligible for benefits
308 Pre-Award Survey
309 Plan Termination
Date on which the plan terminated
310 Date of Closing
The date a property is sold
311 Latest Receiving Date/Cutoff Date
312 Salary Deferral
Date on which the subscriber begins to defer a portion of their salary
313 Cycle
Range of dates as they pertain to a period of time
314 Disability
Range of dates on which the physical or mental condition rendered the subscriber or dependent disabled
315 Offset
Range of dates for which the subscriber or dependent will be receiving other income
316 Prior Incorrect Date of Birth
The incorrect date of birth that was previously transmitted
317 Corrected Date of Birth
Replaces previously transmitted incorrect date of birth
318 Added
319 Failed
320 Date Foreclosure Proceedings Instituted
The date the first legal action is taken to terminate an owner’s interest in realty begins
321 Purchased
Date product/extended coverage was purchased
322 Put into Service
Date product, subassembly, or replacement part was put in-service
323 Replaced
324 Returned
325 Disbursement Date
326 Guarantee Date
327 Quarter Ending
328 Changed
329 Terminated
Any condition previously reported by the carrier as preventing the completion of a move or service has been terminated
330 Referral Date
The date when an educational official or teacher recommends that a student be evaluated for placement in a special education or other program
331 Evaluation Date
The date on which a student was assessed for placement in a special education or other program
332 Placement Date
The date which identifies when a student was enrolled in a special education or other program
333 Individual Education Plan (IEP)
The date on which the plan specifying the special education instruction and services which a student is to receive was approved
334 Re-evaluation Date
The date on which the student’s placement in special education or other programs will be re-assessed
335 Dismissal Date
The date on which the student exited from a special education or other program
336 Employment Begin
Date on which the subscriber or dependent became employed
337 Employment End
Date on which the subscriber or dependent ceased to be employed
338 Medicare Begin
Date on which Medicare benefits went into effect
339 Medicare End
Date on which Medicare benefits ceased to be in effect
340 Consolidated Omnibus Budget Reconciliation Act (COBRA) Begin
Date on which COBRA benefits begin
341 Consolidated Omnibus Budget Reconciliation Act (COBRA) End
Date on which COBRA benefits end
342 Premium Paid to Date Begin
Date for which premium began to be applied
343 Premium Paid to Date End
Date for which premium is paid through
344 Coordination of Benefits Begin
Date on which Coordination of Benefits begin
345 Coordination of Benefits End
Date on which Coordination of Benefits end
346 Plan Begin
Date on which the plan begins
347 Plan End
Date on which plan ends
348 Benefit Begin
Date on which the subscriber’s or dependent’s benefit begin
349 Benefit End
Date on which the subscriber’s or dependent’s benefit ends
350 Education Begin
Date on which the subscriber or dependent became a student
351 Education End
Date on which the subscriber or dependent ceased to be a student
352 Primary Care Provider Begin
Date on which the subscriber’s or dependent’s primary care provider became effective
353 Primary Care Provider End
Date on which the primary care provider’s service ended
354 Illness Begin
Date on which illness began
355 Illness End
Date on which illness ended
356 Eligibility Begin
Date on which eligibility begins
357 Eligibility End
Date on which eligibility ends
358 Cycle Begin
Date on which the cycle begins
359 Cycle End
Date on which the cycle ends
360 Initial Disability Period Start
Date on which the disability begins
361 Initial Disability Period End
Date on which the disability ends
362 Offset Begin
Date subscriber or dependent begins receiving other income
363 Offset End
Date other income benefits cease
364 Plan Period Election Begin
Date on which the pledged contribution begins
365 Plan Period Election End
Date on which the pledged contribution ended
366 Plan Period Election
Range of dates for which the subscriber has pledged to contribute toward a benefit
367 Due to Customer
Date an item is due to a customer
368 Submittal
Date an item was submitted to a customer
369 Estimated Departure Date
370 Actual Departure Date
371 Estimated Arrival Date
372 Actual Arrival Date
373 Order Start
374 Order End
Point after which data can no longer be used (or becomes invalid for use)
375 Delivery Start
The date that deliveries will begin
376 Delivery End
The date that deliveries will end
377 Contract Costs Through
Date through which the costs reported in the contractor’s request for progress payment are current
378 Financial Information Submission
Date of the submission of contractor financial information
379 Business Termination
380 Applicant Signed
381 Cosigner Signed
382 Enrollment
383 Adjusted Hire
Date of rehire is adjusted to give an employee credit for prior years of service, after a break in service has occurred
384 Credited Service
Range of employment service used to determine the amount of plan benefits due the employee
385 Credited Service Begin
The start date from which an employee’s length of service, as defined in the plan document, will be calculated
386 Credited Service End
The end date to be used in the calculation of an employee’s length of service, as defined in the plan document
387 Deferred Distribution
Date to which the participant has elected to defer the distribution of plan benefits (for lump sum payments)
388 Payment Commencement
Date of the initial benefit payment (for installment payments)
389 Payroll Period
The applicable payroll date for the financial transaction
390 Payroll Period Begin
The start date of the payroll cycle for the financial transaction
391 Payroll Period End
The end date of the payroll cycle for the financial transaction
392 Plan Entry
Date the employee’s participation in the plan is effective
393 Plan Participation Suspension
Date the participant is suspended from the plan
394 Rehire
Date the participant is rehired, after termination
395 Retermination
Date the participant ends employment, after being rehired
396 Termination
Date the participant ends employment
397 Valuation
The date when the participant’s total account balance is calculated
398 Vesting Service
Range of employment service used to determine vesting for distribution of plan benefits
399 Vesting Service Begin
The start date from which an employee’s vesting percentage, as defined in the plan document, will be calculated
400 Vesting Service End
401 Duplicate Bill
402 Adjustment Promised
403 Adjustment Processed
404 Year Ending
405 Production
Used to identify dates and times that operations or processes were performed
406 Material Classification
Used to identify dates and times materials were classified or reclassified
408 Weighed
409 Date of Deed in Lieu
The date a voluntary conveyance of a property by deed in lieu is recorded
410 Date of Firm Commitment
The date an obligation to ensure the mortgage is issued
411 Expiration Date of Extension to Foreclose
The last day of a given time limit to commence foreclosure
412 Date of Notice to Convey
The date of the authorization to assign the contractual rights of a mortgage
413 Date of Release of Bankruptcy
The date of release from bankruptcy status
414 Optimistic Early Start
Best case earliest date a task or activity can begin
415 Optimistic Early Finish
Best case earliest date a task or activity can end
416 Optimistic Late Start
Best case latest date a task or activity can begin
417 Optimistic Late Finish
Best case latest date a task or activity can end
418 Most Likely Early Start
Most likely earliest date a task or activity can begin
419 Most Likely Early Finish
Most likely earliest date a task or activity can end
420 Most Likely Late Start
Most likely latest date a task or activity can begin
421 Most Likely Late Finish
Most likely latest date a task or activity can end
422 Pessimistic Early Start
Worst case earliest date a task or activity can begin
423 Pessimistic Early Finish
Worst case earliest date a task or activity can end
424 Pessimistic Late Start
Worst case latest date a task or activity can begin
425 Pessimistic Late Finish
Worst case latest date a task or activity can end
426 First Payment Due
427 First Interest Payment Due
428 Subsequent Interest Payment Due
429 Irregular Interest Payment Due
430 Guarantor Received
431 Onset of Current Symptoms or Illness
Date first symptoms appeared
432 Submission
Date on which claim billing information was sent to payer
433 Removed
434 Statement
Date on which billing document was created
435 Admission
Date of entrance to a health care establishment
436 Insurance Card
437 Spouse Retirement
Date on which patient’s husband or wife has retired from his or her place of employment
438 Onset of Similar Symptoms or Illness
Date symptoms related to current illness first appeared
439 Accident
Date mishap occurred
440 Release of Information
Date patient signified it was acceptable to distribute pertinent information to other parties
441 Prior Placement
Date medical device was last placed or arranged
442 Date of Death
Date life terminated
443 Peer Review Organization (PRO) Approved Stay
Start and end date of approved confinement
444 First Visit or Consultation
Date patient first sought medical assistance
445 Initial Placement
Date medical device was positioned or arranged
446 Replacement
Date medical device was reinstalled or rearranged
447 Occurrence
Date on which an event happened
448 Occurrence Span
Start and end date on which a span of events happened
449 Occurrence Span From
Date on which span of events started
450 Occurrence Span To
Date on which span of events ended
451 Initial Fee Due
Date the first of one or more payments is due
452 Appliance Placement
Date orthodontic devices were arranged
453 Acute Manifestation of a Chronic Condition
Date serious symptoms were exhibited for a long term illness
454 Initial Treatment
Date medical treatment first began
455 Last X-Ray
Date of the most recent x-ray
456 Surgery
Date on which operation was performed
457 Continuous Passive Motion (CPM)
Date patient began using a device to provide uninterrupted motion not produced by active efforts
458 Certification
Date of a document attesting to a fact
459 Nursing Home From
Date on which patient entered nursing home
460 Nursing Home To
Date on which patient was released from nursing home
461 Last Certification
Date of the most recent document attesting to a fact
462 Date of Local Office Approval of Conveyance of Occupied Real Estate Property
The date local office approves of the transfer of an occupied property
463 Begin Therapy
Date treatment of physical or mental disorder started
464 Oxygen Therapy From
Date treatment with oxygen started
465 Oxygen Therapy To
Date treatment with oxygen ceased
466 Oxygen Therapy
Begin and end dates of treatment with oxygen
467 Signature
Date on which the accompanying signature was received
468 Prescription Fill
Date on which drug order was filled
469 Provider Signature
Date supplier of medical service signified the service in question was, in fact, provided
470 Date of Local Office Certification of Conveyance of Damaged Real Estate Property
The date local office approves of the transfer of a damaged property or the date of the mortgagee’s certification that adequate fire insurance was not obtainable
471 Prescription
Date on which prescription was written
472 Service
473 Medicaid Begin
Date patient became eligible for Medicaid benefits
474 Medicaid End
Date patient no longer eligible for Medicaid benefits
475 Medicaid
Start and end of effective period for Medicaid
476 Peer Review Organization (PRO) Approved Stay From
Date start of confinement was approved
477 Peer Review Organization (PRO) Approved Stay To
Date confinement approval ceased
478 Prescription From
Start of prescription period
479 Prescription To
End of prescription period
480 Arterial Blood Gas Test
Date of test to determine gas content in blood circulating from the heart, at rest, breathing room air
481 Oxygen Saturation Test
Date on which oxygen saturation testing occurred
482 Pregnancy Begin
Date pregnancy estimated to begin
483 Pregnancy End
Date pregnancy end, whether normal or abnormal delivery
484 Last Menstrual Period
485 Injury Begin
Date damage was inflicted to the body by an external source
486 Injury End
Date damage inflicted to the body by an external source ceased
487 Nursing Home
Facility for those unable to care for themselves
488 Collateral Dependent
Range of collateral dependent coverage
489 Collateral Dependent Begin
Date on which collateral dependent coverage begins
490 Collateral Dependent End
Date on which collateral dependent coverage ends
491 Sponsored Dependent
Range of sponsoring dependent coverage
492 Sponsored Dependent Begin
Date on which sponsored dependent coverage begins
493 Sponsored Dependent End
Date on which sponsored dependent coverage ends
494 Deductible
Date for which deductible is applied
495 Out-of-Pocket
Date for which out of pocket is applied
496 Contract Audit Date
497 Latest Delivery Date at Pier
498 Mortgagee Reported Curtailment Date
The date the mortgagee failed to meet a mandatory time requirement
499 Mortgagee Official Signature Date
The date the mortgagee’s representative signs the claim for mortgage insurance benefits form
500 Resubmission
Date when original transaction should be resubmitted for further consideration
501 Expected Reply
Date when response may be expected
502 Dropped to Less than Half Time
Date on which the student ceased to be enrolled at least half time
503 Repayment Begin
Date on which repayment of the loan begins
504 Loan Servicing Transfer
Date on which the loan is transferred from one servicer to another servicer
505 Loan Purchase
Date on which the ownership of the loan changes
506 Last Notification
Date on which the lender was last notified of the less-than-half time information
507 Extract
Date on which the file was extracted from the database
508 Extended
The extended date for a performance requirement
509 Servicer Signature Date
The date an authorized representative of the lender servicing the mortgage signs the claim for mortgage insurance benefits form
510 Date Packed
511 Shelf Life Expiration
512 Warranty Expiration
513 Overhauled
514 Transferred
515 Notified
516 Discovered
517 Inspected
518 Voucher (Date of)
519 Date Bankruptcy Filed
Date of last bankruptcy action
520 Date of Damage
The date that the property became damaged
521 Date Hazard Insurance Policy Cancelled
The date the hazard insurance policy was cancelled
522 Expiration Date to Submit Title Evidence
The last day of an approved extension to submit title evidence without penalty
523 Date of Claim
The date the claim form is prepared
524 Date of Notice of Referral for Assignment
The date mortgagors are notified in writing that it is their lender’s opinion that they are qualified for an assignment program and that their defaulted mortgage should be assigned
525 Date of Notice of Probable Ineligibility for Assignment
The date mortgagors are notified in writing that it is their lender’s opinion that they are not qualified for an assignment program but they may apply directly to the program sponsor for consideration
526 Date of Foreclosure Notice
The date the mortgagee notifies the mortgage insurer that foreclosure has been initiated
527 Expiration of Foreclosure Timeframe
The last day of an extension of the time requirement to institute foreclosure proceedings on an insured mortgage
528 Date Possessory Action Initiated
The date the mortgagee initiates action to take possession of a property secured by a mortgage in default
529 Date of Possession
The date a mortgagee acquires possession of a property secured by a mortgage in default
530 Date of Last Installment Received
531 Date of Acquisition of Title
The date the mortgagee acquires good and marketable title to a property secured by a mortgage in default
532 Expiration of Extension to Convey
The last day of an extension of the time requirement to convey a property
533 Date of Assignment Approval
The date approval is given to assign the contract rights of a mortgage
534 Date of Assignment Rejection
The date a request to assign the contract rights of a mortgage is rejected
535 Curtailment Date from Advice of Payment
The date to which interest was curtailed
536 Expiration of Extension to Submit Fiscal Data
The date of the expiration of extension given to submit fiscal data
537 Date Documentation, or Paperwork, or Both Was Sent
538 Makegood Commercial Date
539 Policy Effective
540 Policy Expiration
541 Employee Effective Date of Coverage
542 Claim Administrator Notified of Employee Legal Representation
543 Last Premium Paid Date
544 Employer Knowledge of the Injury
545 Claim Administrator Knowledge of the Injury
546 Date of Maximum Medical Improvement
547 Date of Loan
548 Date of Advance
549 Beginning Lay Date
First date a vessel may call at the port
550 Certificate Effective
551 Benefit Application Date
552 Actual Return to Work
553 Released Return to Work
554 Ending Lay Date
Date by which the vessel will call at the port
555 Employee Wages Ceased
556 Last Salary Increase
557 Employee Laid Off
558 Injury or Illness
559 Oldest Unpaid Installment
The due date of the oldest complete mortgage payment that has not been paid
560 Preforeclosure Acceptance Date
The date that the mortgagor and the mortgagee accepts a preforeclosure acceptance plan
561 Preforeclosure Sale Closing Date
The date that the mortgagor and the mortgagee accept a preforeclosure sales closing plan
562 Date of First Uncured Default
563 Date Default Was Cured
564 Date of First Mortgage Payment
565 Date of Property Inspection
566 Date Total Amount of Delinquency Reported
567 Date Outstanding Loan Balance Reported
568 Date Foreclosure Sale Scheduled
569 Date Foreclosure Held
570 Date Redemption Period Ends
571 Date Voluntary Conveyance Accepted
The date voluntary conveyance of the property by the mortgagee holding the defaulted mortgage is accepted by the Federal Housing Commissioner
572 Date Property Sold
573 Date Claim Paid
574 Action Begin Date
The date a resolution action such as scheduling a repayment plan or a delay action such as Chapter 7 bankruptcy filing begins
575 Projected Action End Date
576 Action End Date
577 Original Maturity Date
578 Date Referred to Attorney for Foreclosure
579 Planned Release
580 Actual Release
581 Contract Period
582 Report Period
583 Suspension
584 Reinstatement
585 Report
586 First Contact
587 Projected Foreclosure Sale Date
589 Date Assignment Filed for Record
The date the transfer of the contract right to real estate is filed for record with the recording authority
590 Date of Appraisal
The date the value of a property is assessed
591 Expiration Date of Extension to Assign
The last day of a given time limit to assign the contractual rights of a mortgage
592 Date of Extension to Convey
The last day of a given time limit to complete the transfer of real property
593 Date Hazard Insurance Policy Refused
The date the insurance carrier refused to renew the policy on a property
594 High Fabrication Release Authorization
The date of the purchaser’s program number that authorizes the highest amount of material production
595 High Raw Material Authorization
The date of the purchaser’s program number that authorizes the highest amount of raw material or purchased components in their original state to be secured for production
596 Material Change Notice
597 Latest Delivery Date at Rail Ramp
598 Rejected
599 Repayment Schedule Sent
600 As Of
601 First Submission
602 Subsequent Submission
603 Renewal
604 Withdrawn
606 Certification Period Start
607 Certification Revision
608 Continuous Coverage Date(s)
609 Prearranged Deal Match
610 Contingency End
611 Oxygen Therapy Evaluation
The date the patient was last examined by the physician to determine the need for oxygen therapy
612 Shut In
The date when the valves are closed or the pump is stopped at the wellhead
613 Allowable Effective
The date the report is effective for allowable purposes
614 First Sales
615 Date Acquired
616 Interviewer Signed
617 Application Logged Date
618 Review Date
619 Decision Date
620 Previously Resided
621 Reported
622 Checked
623 Settled
624 Presently Residing
625 Employed in this Position
626 Verified
627 Second Admission Date
Date of second admission to a health care facility which occurred during the service period of this claim
629 Account Opened
630 Account Closed
631 Property Acquired
632 Property Built
633 Employed in this Profession
634 Next Review Date
635 Initial Contact Date
636 Date of Last Update
637 Second Discharge Date
Date of second discharge from a health care facility which occurred during the service period of this claim
638 Date of Last Draw
640 Complaint
641 Option
642 Solicitation
643 Clause
644 Meeting
646 Rental Period
647 Next Pay Increase
648 Period Covered by Source Documents
649 Document Due
650 Court Notice
651 Expected Funding Date
652 Assignment Recorded
653 Case Reopened
655 Previous Court Event
656 Last Date to Object
657 Court Event
658 Last Date to File a Claim
659 Case Converted
660 Debt Incurred
661 Judgment
662 Wages Start
663 Wages End
664 Date Through Which Property Taxes Have Been Paid
665 Paid Through Date
666 Date Paid
667 Anesthesia Administration
668 Price Protection
669 Claim Incurred
The date a debt or obligation arises or is incurred
670 Book Entry Delivery
671 Rate Adjustment
672 Next Installment Due Date
673 Daylight Overdraft Time
Time a Fed Wire is processed by the Federal Reserve
674 Presentment Date
Date a Letter of Credit is presented
675 Negotiated Extension Date
New date to which a Letter of Credit extension is negotiated
681 Remittance
682 Security Rate Adjustment
683 Filing Period
684 Review Period End
685 Requested Settlement
686 Last Screening
687 Confinement
688 Arrested
689 Convicted
690 Interviewed
691 Last Visit
692 Recovery
693 Time in U.S.
694 Future Period
Range of future activity
695 Previous Period
Range of previous activity
696 Interest Paid To
697 Date of Seizure
699 Setoff
Date creditor reduced claim by amount of debtor’s claim against creditor
700 Override Date for Settlement
701 Settlement Date (From Interline Settlement System (ISS) only)
702 Sending Road Time Stamp
703 Retransmission Time Stamp
704 Delivery Appointment Date and Time
The date and time associated with an appointment number
705 Interest Paid Through
706 Date Material Usage Suspended
707 Last Payment Made
708 Past Due
709 Analysis Month Ending
710 Date of Specification
711 Date of Standard
712 Return to Work Part Time
713 Paid-through Date for Salary Continuation
714 Paid-through Date for Vacation Pay
715 Paid-through Date for Accrued Sick Pay
716 Appraisal Ordered
717 Date of Operation
718 Best Time to Call
719 Verbal Report Needed
720 Estimated Escrow Closing
721 Permit Year
722 Remodeling Completed
723 Current Month Ending
724 Previous Month Ending
725 Cycle to Date
726 Year to Date
727 On Hold
728 Off Hold
729 Facsimile Due By
730 Reporting Cycle Date
731 Last Paid Installment Date
732 Claims Made
Date that determines Liability coverage under a Claims Made policy
733 Date of Last Payment Received
734 Curtailment Date
736 Pool Settlement
737 Next Interest Change Date
738 Most Recent Hemoglobin or Hematocrit or Both
739 Most Recent Serum Creatine
740 Closed
741 Therapy
742 Implantation
743 Explantation
744 Date Became Aware
745 First Marketed
746 Last Marketed
747 New Due Date of First Payment to Principal and Interest
748 New Maturity Date
749 Current
750 Expected Problem Resolution
The date and time by which resolution of a problem is expected to occur
751 Alternate Problem Resolution
The alternate date and time by which resolution of a problem should occur, if the expected problem resolution date and time cannot be met
752 Fee Capitalization
753 Interest Capitalization
754 Next Payment Due
755 Conversion to Repayment
756 End of Grace Period
757 School Refund
758 Simple Interest Due
759 Date Practice Ceased
760 Printed
761 Date Practice Established
762 Drop Action Date
764 Most Recent Renewal
765 Original
766 Outside Auditor’s Report
769 Pre-certification Date
770 Back on Market
771 Status
772 Benefit Adjustment Start
773 Off-Market
774 Tour
775 Benefit Adjustment End
776 Listing Received
777 Benefit Adjustment Period
778 Anticipated Closing
779 Last Publication
780 Sold Book Publication
Publication Date of Multiple Listing Book of Sold Property
781 Occupancy
782 Contingency
783 Percolation Test
784 Septic Approval
785 Title Transfer
786 Open House
787 Benefit Credit Period
788 Benefit Transfer Period
789 Homestead
790 Sanction
791 Tail Coverage Begin
Extension of liability coverage begin date
792 Tail Coverage End
Extension of liability coverage end date
793 Training Begin
794 Training End
795 Verification Received
796 Verification Sent
797 State Residency Date
798 Effective Date of the Routing File
799 Test Data Analysis
800 Midpoint of Performance
801 Acquisition Date
802 Date of Action
803 Paid in Full
804 Refinance
805 Voluntary Termination
806 Customer Order
807 Stored
808 Selected
809 Posted
810 Document Received
811 Rebuilt
812 Marriage
813 Customs Entry Date
814 Payment Due Date
815 Maturity Date
816 Trade Date
817 Gallons Per Minute (GPM) Test Performed
818 British Thermal Unit (BTU) Test Performed
819 Last Accounts Filed at Public Registration Agency
820 Real Estate Tax Year
821 Final Reconciliation Value Estimate as of
822 Map
823 Opinion
824 Version
825 Original Due Date
826 Incumbency Period
827 Audience Deficiency Period
828 Aired Date
830 Schedule
831 Paid Through Date for Minimum Payment
832 Paid Through Date for Total Payment
840 Election
841 Engineering Data List
842 Last Production
843 Not Before
844 Not After
845 Initial Claim
846 Benefits Paid
847 Wages Earned
848 Adjusted Start
849 Adjusted End
850 Revised Adjusted Start
851 Revised Adjusted End
853 Field Test
854 Mortgage Note Date
855 Alternative Due Date
856 First Payment Change
857 First Rate Adjustment
858 Alternate Base Period
859 Prior Notice
860 Appointment Effective
861 Appointment Expiration
862 Company Termination
863 Continuing Education Requirement
864 Distributor Effective
865 Distributor Termination
866 Examination
867 Incorporation Dissolution
868 Last Follow-up
869 License Effective
870 License Expiration
871 License Renewal
872 License Requested
873 Mailed
874 Paperwork Mailed
875 Previous Employment
876 Previous Employment End
877 Previous Employment Start
878 Previous Residence
879 Previous Residence End
880 Previous Residence Start
881 Request
882 Resident License Effective
883 Resident License Expiration
884 State Termination
885 Texas Line Termination
900 Acceleration
901 Adjusted Contestability
903 Application Entry
904 Approval/Offer
905 Automatic Premium Loan
906 Collection
907 Confinement End
908 Confinement Start
909 Contestability
910 Flat Extra End
911 Last Activity
912 Last Change
913 Last Episode
914 Last Meal
915 Loan
916 Application Status
917 Maturity
918 Medical Information Signature
919 Medical Information System
920 Note
921 Offer Expiration
922 Original Receipt
923 Placement
924 Placement Period Expiration
925 Processing
926 Recapture
927 Re-entry
928 Reissue
930 Requalification
931 Reinsurance Effective
932 Reservation of Facility
933 Settlement Status
934 Table Rating End
935 Termination of Facility
936 Treatment
937 Department of Labor Wage Determination Date
938 Order
939 Resolved
940 Execution Date
941 Capitation Period Start
942 Capitation Period End
943 Last Date for a Government Agency to File a Claim
944 Adjustment Period
945 Activity
946 Mail By
947 Preparation
948 Payment Initiated
949 Payment Effective
950 Application
951 Reclassification
952 Reclassification (Exit Date)
953 Post-Reclassification
954 Post-Reclassification (First Report Card)
955 Post-Reclassification (First Semi-annual)
956 Post-Reclassification (Second Semi-annual)
957 Post-Reclassification (End of Second Year)
960 Adjusted Death Benefit
961 Anniversary
962 Annuitization
963 Annuity Commencement Date
Expiration of annuity accumulation contract
964 Bill
965 Calendar Anniversary
Adjusted plan anniversary date
966 Contract Mailed
967 Early Withdrawal
Pre age 59 withdrawal from qualified plan
968 Fiscal Anniversary
969 Income
Date annuity payments commence
970 Initial Premium
971 Initial Premium Effective
972 Last Premium Effective
973 Minimum Required Distribution
Internal Revenue Service required latest distribution start date
974 Next Anniversary
975 Notice
976 Notification of Death
977 Partial Annuitization
978 Plan Anniversary
Anniversary date adjusted to nearest business day
979 Policy Surrender
980 Prior Contract Anniversary
981 Prior Contract Issue
982 Signature Received
983 Tax
984 Benefit Period
985 Month to Date
986 Semiannual Ending
987 Surrender
988 Plan of Treatment Period
989 Prior Hospitalization Date(s) Related to Current Service(s)
990 Original Name Change
992 Date Requested
993 Request for Quotation
The reference date associated with a specifically numbered request for quotation
994 Quote
The date on which a (price) quote was rendered
995 Recorded Date
996 Required Delivery
A date on which or before, ordered goods or services must be delivered
997 Quote to be Received By
A date on which or before a quote must be received at a location specified in an RFQ
998 Continuation of Pay Start Date
999 Document Date
AA1 Estimated Point of Arrival
AA2 Estimated Point of Discharge
AA3 Cancel After, Ex Country
AA4 Cancel After, Ex Factory
AA5 Do Not Ship Before, Ex Country
AA6 Do Not Ship Before, Ex Factory
AA7 Final Scheduled Payment
AA8 Actual Discharge
AA9 Address Period
AAA Arrival in Country
AAB Citation
AAC Suspension Effective
AAD Crime
AAE Discharge – Planned
AAF Draft
AAG Due Date
AAH Event
AAI First Involvement
AAJ Guarantee Period
AAK Income Increase Period
AAL Installment Date
AAM Last Civilian Flight
AAN Last Flight
AAO Last Insurance Medical
AAP Last Military Flight
AAQ Last Physical
AAR License
AAS Medical Certificate
AAT Medication
AAU Net Worth Date
AAV Next Activity
AAW Ownership Change
AAX Ownership Period
AAY Rate Date
AAZ Requested Contract
AB1 Requested Offer
AB2 Sales Period
AB3 Tax Year
AB4 Time Period
AB5 Travel
AB6 Treatment End
AB7 Treatment Start
AB8 Trust
AB9 Worst Time to Call
ABA Registration
ABB Revoked
ABC Estimated Date of Birth
ABD Last Annual Report
ABE Legal Action Started
ABF Lien
ABG Payment Period
ABH Profit Period
ABI Registered
ABK Consolidated
Date businesses consolidated or merged
ABL Board of Directors Not Authorized As Of
ABM Board of Directors Incomplete As Of
ABN Manager Not Registered As Of
ABO Citizenship Change
ABP Participation
ABQ Capitalization
ABR Registration of Board of Directors
ABS Ceased Operations
ABT Satisfied
ABU Terms Met
ABV Asset Documentation Expiration
ABW Credit Documentation Expiration
ABX Income Documentation Expiration
ABY Product Held Until
ACA Immigration Date
ACB Estimated Immigration Date
ACC Current Disability Period Start
ACD Current Disability Period End
ACE Current Disability Period Last Day Worked
ACF Benefit Type Gross Weekly Amount Effective
ACG Benefit Type Net Weekly Amount Effective
ACH Benefit Type Period Start
ACI Benefit Type Period End
ACJ Benefit Debit Start
ACK Acknowledgment
ACL Benefit Debit End
ACM Benefit Credit Start
ACN Benefit Credit End
ACO Benefit Transfer Start
ACP Benefit Transfer End
ACQ Wage Effective
ACR Full Denial Effective
ACS Full Denial Rescission
ACT Payment Issue
ACU Payment Period Start
ACV Payment Period End
ACW Employer Reported Injury To Claim Administrator
ACX Survey Year
ACZ Controvert Date
ADA Billed Through
ADB Business Control Change
ADC Court Registration
ADD Annual Report Due
Date annual report will be due with state
ADE Claim Notification Received
ADF Conversion Privilege End
ADG Dividend Applied
ADH In-force
ADI Paid-up
ADJ Premium Change
ADK Policy Effective on or before
ADL Asset and Liability Schedule
ADM Annual Report Mailed
Date annual report was mailed when last filed with state corporate authorities
ADN Policy Effective on or after
ADR Annual Report Filed
Date annual report last filed with state corporate authorities
ADS Audit Period After Split Date
ADT Audit Period Prior to Split Date
ADU Exposure Source Period
ADV Subcontractor Period of Hire
ADW Divorce
ADX Power of Attorney
ADY Uniform Gifts to Minors Account Established
AEA Medicare Part A Eligibility Begin Date
AEB Medicare Part A Eligibility End Date
AEC Medicare Part A Coverage Effective Date
AED Medicare Part A Termination Date
AEE Medicare Part B Eligibility Begin Date
AEF Medicare Part B Eligibility End Date
AEG Medicare Part B Coverage Effective Date
AEH Medicare Part B Termination Date
AEI Loading Period
AEK Date on which Assets Judged Insufficient to Pay Creditors
AEL Employees Temporarily Laid Off Begin Period
AEM Employees Temporarily Laid Off End Period
AEN First Published
AEO Forecast Period Start
AEP Forecast Period End
AEQ Investigation Start
AER Investigation End
AES Last Published
AET Latest Balance Sheet
AEU Share Price
AEV Stop Distribution
AEW Maximum Credit Date
Date of highest credit provided to entity by a vendor
AEX Founding Date
AEY Repayment Plan Start Date
AFA Medicare Part D Eligibility Begin Date
AFB Medicare Part D Eligibility End Date
AFC Medicare Part D Coverage Effective Date
AFD Medicare Part D Termination Date
ARD Annual Report Delinquency
Date annual report will be delinquent with state corporate authorities
AWH Withheld Date
BAA Compliance Audit
BAB Contractor Safety Performance Evaluation
BAC Contractor Safety Procedures Review
BAD Date of Equipment Inspection
BAE Date of Safety Inspection
BAF Employees Participation Plan Review
BAG Expected Completion of Changes Resulting from Compliance Audit
BAH Expected Completion of Changes Resulting from Process Hazard Analysis
BAI Expected Completion of Changes Resulting from Hazard Review
BAJ Hazard Review Completion
BAK Hot Work Permit Procedures Review
BAL Investigation
BAM Maintenance Procedures Review
BAN Management of Change Procedures Review
BAO Operating Procedures Review
BAP Safety Information Review
BAQ Training
BAR Training Program Review
BED Billback End Date
BEE Program Performance End Date
BES Program Performance Start Date
BGP Beginning of Grace Period
BIA Billing Activities
Date of earliest billing action through date of latest billing action
BIP Beginning of Interest Paid After Claim
BSD Billback Start Date
CAD Changed Accounting Date
CCR Customs Cargo Release
CDD Contract Definitization Date
CDT Maintenance Comment
CEA Formation
CEB Continuance
CEC Merger
CED Year Due
CEE Next Annual Meeting
CEF End of Last Fiscal Year
CEH Year Beginning
CEJ Started Doing Business
CEK Sworn and Subscribed
CEL Calendar Year
CEM Asset
CEN Inactivity
CEO High Capital Year
CLO Closing Date of First Balance Sheet
CLU Closed Until
COM Compliance
CON Converted into Holding Company
COS Care of Supplies in Storage Inspection Date
Identifies the date that items in storage were last inspected
CRV Claim Revised
CUR Current List
DAF Account Frozen
DDO Declaration
DEE Deed Not Available
DEL Delete
DET Detrimental Information Received
DFF Deferral
DFS Departure From Specification
DIL Deed In Lieu (DIL) Approved
DIP Delayed Interest Paid Through
DIS Disposition
DLC Date of Last Contact
DOA Date of Abandonment
DOD Date of Delinquency
DOI Delivery Order Issued
DOR Repossession
DSP Disposal
DTC Deed and Title Received
DTD Technical Data Supply By
DTQ Deed and Title Requested
E01 Tenure Decision
E02 Most Recent Position Change
E03 Fee Payment
E04 Start Date for Continuous Employment
E05 Start Date for Current Position
E06 Start Date for Original Position
E07 Fiscal Year
ECD Estimated Construction Date
ECF Estimated Completion – First Prior Month
ECS Estimated Completion – Second Prior Month
ECT Estimated Completion – Third Prior Month
EDA Affirmed
EDB Auction
EDC Authorized
EDD Contribution
EDE Executed
EDF Forgiven
EDG Presented
EDH Legislative Session
EDI Organized
EDJ Pledged
EDK Primary Election
EDL Qualified
EDM Refunded
EDN Rescinded
EDO Restructured From
EDP Vote
EKD Employer Knowledge of the Disability
EPP Estimate Preparation
ESC Estimate Comment
ESF Estimated Start – First Prior Month
ESS Estimated Start – Second Prior Month
EST Estimated Start – Third Prior Month
ETP Earliest Filing Period
EXO Exposure
EXP Export
FAC Facility Latest Billing Action
Date of most recent billable service provided during a spell of illness
FEB Facility Earliest Billing Action
Date of the earliest billable service provided during a spell of illness
FFI Financial Information
FFO First Order
FIA Final Interest Accrual
FPE Funding Period – End
FPS Funding Period – Start
FSE Free Service Call End Date
FSS Free Service Call Start Date
GRD Graduated
HHD Home Health Date of Earliest Billable Action
Date of the earliest billable service provided by a home health provider during an episode
HHE Home Health Episode
Dates during which a patient is under the care of a home health agency
HHL Home Health Date of Latest Billable Action
Date of the most recent billable service provided by a home health provider during an episode
ICF Converted to Electronic Date
IDG Insolvency Discharge Granted
IFH Initial Federal Housing Authority Claim Payment
III Incorporation
ILU Image Last Update Date
IMB Imbalance Period
IMP Import
INC Incident
INT Inactive Until
IPS Interest on Presale Start
IVA Initial Veterans Administration Claim Payment
KEV Key Event Fiscal Year
KEW Key Event Calendar Year
LAM Last Annual Meeting
LAS Last Check for Balance Sheet Update
LCC Last Capital Change
Date capital stock was last modified
LEA Letter of Agreement
LEL Letter of Liability
LIQ Liquidation
LLP Low Period
LOG Equipment Log Entry
LPC List Price Change
LSC Legal Structure Change
LSD Last Submission Date
LTP Latest Filing Period
MRR Meter Reading
MSD Latest Material Safety Data Sheet Date
NAM Present Name
NFD Negotiated Finish
NOD Notice of Delinquency (NOD) Received
NRG Not Registered
NSD Negotiated Start
OCD Organic Certification Date
The date that the organic certification was issued by the organic certification agency
ORG Original List
PBC Present Control
PCP Primary Coverage Claim Paid
PCS Primary Coverage Claim Submission
PCT Price Changes Allowed From Date
PCU Price Changes Allowed To Date
PDE Partial Denial Effective
PDR Partial Denial Rescission
PDS Correct Program Start Date
PDT Correct Program End Date
PDU Correct Contract Start Date
PDV Privilege Details Verification
PDW Correct Contract End Date
PED Program End Date
PLS Present Legal Structure
PPC Pool Policy Claim Submission
PPD Post Paid Date
The last date a tax authority posted tax payments
PPP Peak Period
PRD Previously Reported Date of Birth
PRR Presented to Receivers
PSA Property Sale Approved
PSC Property Sale Closed
PSD Program Start Date
PSF Property Sale Confirmation
PTD Paid To Date
PTO Plan to Obsolete
PUD Pick-up Date
RAP Receiver Appointed
REM Remanufacture Date
The date a product was refurbished by renovating and reassembling its components
RES Resigned
RFD Requested Finish
RFF Recovery Finish
RFO Referred From
RNT Rent Survey
RRM Received in the Mail
RRT Revocation
RSD Requested Start
RSS Recovery Start
RTO Referred To
SCV Social Security Claims Verification
SDD Sole Directorship Date
SFH Subsequent Federal Housing Authority Claim Payment
SPD Initial Support Date
STN Transition
SVA Subsequent Veterans Administration Claim Payment
TSR Trade Style Registered
TSS Trial Started
TST Trial Set
VAT Value Added Tax (VAT) Claims Verification
VLU Valid Until
W01 Sample Collected
W02 Status Change
W03 Construction Start
W05 Recompletion
W06 Last Logged
W07 Well Log Run
W08 Surface Casing Authority Approval
W09 Reached Total Depth
W10 Spacing Order Unit Assigned
W11 Rig Arrival
W12 Location Exception Order Number Assigned
W13 Sidetracked Wellbore
WAA Time Employee Began Work
WAY Waybill
XX1 Order Day
Day of week when an order may be placed
XX2 Delivery Day
Day of week when an order delivery will occur
XX3 Order Cut-Off Time
Latest time-of-day when an order may be placed
YXX Programmed Fiscal Year
YXY Programmed Calendar Year
ZZZ Mutually Defined

One Thought on “X12 Date and Time Qualifiers

  1. Your site is an invaluable resource for any person wanting to educate themselves on intriguing subjects!

Leave a Reply

Your email address will not be published.

Post Navigation